Course Managers Update - Around the Greens in September 2021
Published Thursday, 16th September 2021
August was a dry month until the last week when 70mm of
rain was delivered to the course in a two-day deluge. The rain could not have
come at a better time with renovations being completed just a few days prior
and the course closed due to COVID restrictions. The days were warm with an
average maximum of 190C and only three light and one heavy frost.
The
greens were renovated with 16mm hollow tines to a depth of around 100mm. Forty
tonne of USGA top dressing was applied and rubbed in followed by soil amendment
applications. With the rain and a two week closure the greens recovered very
well and are extremely healthy. Poa seed suppression began as scheduled early
in the month with the second application going out at the end of August and the
3rd and final application is scheduled for the end of September.
The tees were cored with 19mm hollow tines while the
course was closed, and I hope to follow up in November. The tees have come
through winter quite well and certainly enjoyed the break during the course
closure. Surfaces are clean of weeds besides the odd stubborn patch of Kikuyu
which should be taken care of with upcoming herbicide applications. Gypsum and
organics will be applied to tees in mid-September.
The fairways
were renovated with 19mm hollow tines during the renovation week. Cores were
then rubbed in with a steel drag mat and the loose debris blown into the rough.
Five tonne of Calcium was spread over the fairways. The height of cut has been
dropped to 10mm to chop out any thatch and Poa, this height will be raised to
12mm once the first Primo application takes place in September. There are still
a few small bare patches from Ground pearl, and I hope to have these areas
turfed as soon as I can get a full team back on site. With some good rain
predicted through this summer I believe we can really start to get the fairways
back into great condition. Extra organic and gypsum applications have and will continue
to be carried out on the 11th fairway in the coming weeks.
Tree root pruning was carried out on a couple of areas on
11th during August and in renovation week arborists removed some
dead trees on the 1st and 16th and some dead wood was
removed from several trees on the 14th fairway.
The earth works for the construction of the 14th path, funded by the NSW Government Local Sport Grant, began during the course closure and the concrete contractors laid the path on the 8th and 9th of September.
Floating wetlands, funded by the Golf NSW Foundation, were
delivered on the 3rd of September and the first of three have been
‘launched’. The wetlands are designed to vegetate ponds, waterways, dams and
water bodies requiring either an aesthetic treatment, habitat production or
water rehabilitation to reduce pollutants and nutrient loads.
Shay Tasker
Course Manager